Use three-phase 200V devices at a factory with no three-phase power supply

If there is no three-phase power receiving at the rental factory or transfer destination, you can consider the configuration of making a three-phase 200V from a single-phase 200V circuit available.

It is a guide to organize the specifications and power supply conditions of the equipment. Actual conformity is determined by confirming the model and site conditions.

First of all, the power transmission and the condition of the machine

  1. Single phase 200V circuit on site:Check the capacity, the position of the switchboard, the contract, the circuit breaker, and the wiring.
  2. Machine: Check whether the three-phase 200V, rated current, start method, and control power supply.
  3. Operation plan: Check how many units are used at the same time, and check the working time and start order.
  4. Location: Check the equipment loading, ventilation, fixed methods, noise and management rules.

Ranges that can be supported by three-phase converters

INV-9600PTV accepts single-phase 200 V or DC within the specified range and supplies three-phase, three-wire 200 V sine-wave power at 50/60 Hz, up to 9.6 kVA. It offers an alternative to waiting for a new utility connection, but requires sufficient input capacity and cannot guarantee startup of every machine.

Determines whether the application or capacity fits, including the motor, control panel, and input equipment. When driving multiple machines simultaneously, check each load.

How to proceed with rental properties and temporary equipment

In the rental factory, please check the conditions of the administrator for dedicated circuit work and installation location from the switchboard first. In the exhibition and test facility, the supply power supply of the venue and the start condition of the equipment will be determined. The wiring work requirements and costs vary depending on the site.

If you want to create a three-phase power supply, we will consider the usage period, the number of machines, the power supply capacity, and future relocation plans.

Information to provide when contacting us

  • Model and nameplate photos of the machine you want to use
  • Start method, simultaneous operation or not
  • Single Phase 200V Circuit Disconnection Board Information
  • Conditions of installation location and construction conditions for rental properties

To design and connect the power circuit, please ask a qualified person who has confirmed the site conditions.

Please contact us from the type of equipment.

If you have a nameplate photo and a single-phase 200V power supply that can be used, you can organize your confirmation.